Third Biennial Report of the Oregon State Highway Commission - novelonlinefull.com
You’re read light novel Third Biennial Report of the Oregon State Highway Commission Part 5 online at NovelOnlineFull.com. Please use the follow button to get notification about the latest chapter next time when you visit NovelOnlineFull.com. Use F11 button to read novel in full-screen(PC only). Drop by anytime you want to read free – fast – latest novel. It’s great if you could leave a comment, share your opinion about the new chapters, new novel with others on the internet. We’ll do our best to bring you the finest, latest novel everyday. Enjoy
Grand Total of Funds Allotted $4,271,515.16 Grand Total of Expenditures 3,597,982.47 ------------- Balance on hand December 1st, 1918 $ 673,532.69
The details of fund allotments and expenditures are set forth in tables as follows:
Table I. Fund Allotments from all sources.
Table II. Summary of Fund Allotments and Fund Expenditures.
Table III. Expenditures Segregated by Counties.
Table IV. Expenditures Segregated under the Headings of General Administrative, Surveys, Construction Engineering, Construction, Equipment and Uncla.s.sified.
Table V. Expenditures for Construction Detailed by Jobs.
Table VI. Expenditures for Surveys Detailed by Jobs.
Table VII. Expenditures for Equipment, Bond Interest and Overhead.
Table VIII. Summary of County Funds Expended by Department.
TABLE I
FUND ALLOTMENTS FROM ALL SOURCES--DECEMBER 1ST, 1916, TO NOVEMBER 30TH, 1918
_One-Quarter Mill Tax Fund_-- Balance on hand Dec. 1, 1916 $ 94,418.14 Turnover January 1, 1917 219,690.98 Turnover January 1, 1918 232,151.39 ----------- Total $ 546,260.51
_Automobile License Fund_-- Turnover October 1, 1917 $150,000.00 Turnover April 1, 1918 300,000.00 Turnover October 1, 1918 125,000.00 ----------- Total $ 575,000.00
_Six Million Dollar Bond Fund_-- Bond Sale, August 7, 1917 $471,300.00 Accrued Interest 2,333.33 Bond Sale, September 12, 1917 472,130.00 Accrued Interest 1,833.33 Bond Sale, March 15, 1918 455,850.00 Accrued Interest 222.22 Bond Sale, July 9, 1918 643,770.00 Accrued Interest 2,606.54 ----------- Total $2,050,045.42
_State and Federal Co-operative Bond Fund_-- Bond Sale, August 18, 1917 $388,040.00 Accrued Interest 2,844.44 Less expenditures by Board of Control 400.00 ----------- Total $ 390,484.44
_County Funds_-- Payments on Vouchers drawn by Department 709,724.79 ----------- Grand Total Funds Allotted to Highway Department, December 1, 1916 to November 30, 1918 4,271,515.16
(For description of the several funds provided for the work of the Highway Department see pages 30 and 31.)
TABLE II
SUMMARY OF FUND ALLOTMENTS AND FUND EXPENDITURES--DECEMBER 1ST, 1916, TO NOVEMBER 30TH, 1918
==============================+=============+=============+=========== | | | Balance Funds | Allotments | Expenditures| December, | | | 1, 1918 ------------------------------+-------------+-------------+----------- One Quarter Mill Tax Fund | $ 546,260.51| $ 528,789.99|$ 17,470.52 Automobile License Fund | 575,000.00| 281,902.67| 293,097.33 Six Million Dollar Bond Fund | 2,050,045.42| 2,049,025.47| 1,019.95 State and Federal Co-operative| | | Bond Fund | 390,484.44| 28,539.55| 361,944.89 ------------------------------+-------------+-------------+----------- Total State Funds |$3,561,790.37|$2,888,257.68|$673,532.69 | | | County Funds | 709,724.79| 709,724.79| ...
------------------------------+-------------+-------------+----------- Grand Total |$4,271,515.16|$3,597,982.47|$673,532.69 ------------------------------+-------------+-------------+-----------
TABLE III
EXPENDITURES SEGREGATED BY COUNTIES (INCLUDING COUNTY FUNDS EXPENDED UNDER STATE SUPERVISION)--DECEMBER 1ST, 1916, TO NOVEMBER 30TH, 1918
===========+===============+===============+=============== County | State Funds | County Funds | Total -----------+---------------+---------------+--------------- Baker | $ 7,578.68 | ... | $ 7,578.68 Benton | 47.56 | $ 479.20 | 526.76 Clackamas | 155,861.10 | 43,091.14 | 198,952.24 Clatsop | 344,387.23 | ... | 344,387.23 Columbia | 488,302.15 | ... | 488,302.15 Coos | 16,967.68 | 170,781.83 | 187,749.51 Crook | 3,053.72 | ... | 3,053.72 Curry | 5,629.24 | ... | 5,629.24 Deschutes | 20,716.37 | ... | 20,716.37 Douglas | 159,769.58 | 173,550.18 | 333,320.76 Gilliam | 35,999.48 | ... | 35,999.48 Grant | 7,468.78 | 291.10 | 7,759.88 Harney | 1,873.45 | ... | 1,873.45 Hood River | 433,928.22 | 3,968.49 | 437,896.71 Jackson | 86,619.88 | ... | 86,619.88 Josephine | 77,998.14 | ... | 77,998.14 Klamath | 819.23 | ... | 819.23 Lake | 15,391.67 | ... | 15,391.67 Lane | 14,529.52 | ... | 14,529.52 Lincoln | 2,997.47 | ... | 2,997.47 Linn | 791.07 | 5.00 | 796.07 Malheur | 866.65 | ... | 866.65 Marion | 5,083.59 | 223,794.99 | 228,878.58 Morrow | 10,863.10 | 1,009.44 | 11,872.54 Polk | 802.92 | 17,200.70 | 18,008.62 Sherman | 3,052.14 | ... | 3,052.14 Tillamook | 68,274.29 | 26,009.84 | 94,284.13 Umatilla | 173,942.50 | 3,542.75 | 177,485.25 Union | 32,188.17 | 78.59 | 32,266.76 Wallowa | 765.07 | ... | 765.07 Wasco | 4,313.79 | 19.45 | 4,333.24 Washington | 246,769.05 | 9,395.00 | 256,164.05 Wheeler | 69,214.78 | 18,233.60 | 87,448.38 Yamhill | 124,958.84 | 18,273.49 | 143,232.33 +---------------+---------------+--------------- Total | $2,621,825.11 | $709,724.79 | $3,331,549.90 -----------+---------------+---------------+---------------
TABLE IV
EXPENDITURES SEGREGATED UNDER THE HEADINGS OF GENERAL ADMINISTRATION, SURVEYS, CONSTRUCTION ENGINEERING, CONSTRUCTION, EQUIPMENT AND UNCLa.s.sIFIED.
=========================+===============+===============+============ Cla.s.sification | Total | State | County | | Funds | Funds -------------------------+---------------+---------------+------------ General Administration | | | and Supervision | $ 97,621.82 | $ 97,621.82 | ...
Surveys and Engineering | | | County Work | 144,086.67 | 137,954.74 | $ 6,131.93 Construction Engineering | 127,805.58 | 127,803.08 | 2.50 Construction | 3,059,657.65 | 2,356,067.29 | 703,590.36 Equipment | 86,717.55 | 86,717.55 | ...
Uncla.s.sified (Interest | | | on Bonds, etc.) | 82,093.20 | 82,093.20 | ...
+---------------+---------------+------------ Grand Total Expenditures | $3,597,982.47 | $2,888,257.68 | $709,724.79 -------------------------+---------------+---------------+------------
TABLE V
EXPENDITURES FOR CONSTRUCTION WORK DETAILED BY JOBS--DECEMBER 1ST, 1916, TO NOVEMBER 30TH, 1918
==================================+=============================+ | TOTALS | +--------------+--------------+ | Estimated | Expended | JOBS | total | to date | | cost of job | | ----------------------------------+--------------+--------------+ Clackamas County: | | | Paving--Oregon City to Canby | $135,000.00 | $102,114.85 | Grading--Canemah Hill Section | 27,500.00 | 24,037.20 | Grading and Rock Crushing--New | 66,000.00 | 63,047.79 | Era | | | Grading--Multnomah Co. Line to | 5,746.80 | 7,746.68 | Oswego | | | Clatsop County: | | | Grading and Paving--Astoria to | 236,000.00 | 96,955.97 | Svensen | | | Macadamizing--Svensen to | 216,000.00 | 210,079.16 | Columbia Co. Line | | | John Day River Bridge east of | 25,000.00 | 21,051.52 | Astoria | | | Plympton Creek Bridge at | 6,413.19 | 6,413.19 | Westport | | | Big Creek Bridge near Knappa | 8,446.70 | 8,446.70 | Little Creek Culvert near Knappa| 929.69 | 929.60 | Miscellaneous charges on work | 247.94 | 247.94 | prior to 1917 | | | Columbia County: | | | Paving--Multnomah Co. Line to | 37,652.59 | 37,652.59 | Scappoose | | | Macadam--Clatsop Co. Line to | 121,000.00 | 118,922.90 | Clatskanie | | | Macadam--Clatskanie to Delena | 142,000.00 | 136,560.40 | Macadam--Delena to Goble | 49,955.08 | 49,955.08 | Macadam--Goble Section | 23,000.00 | 21,478.97 | Grading--Goble Section | 46,262.64 | 46,262.64 | Grading--Rainier Hill Section | 6,350.61 | 6,350.61 | Grading--Beaver Valley Section | 20,978.22 | 20,978.22 | Grading--Deer Island Section | 2,398.10 | 2,398.10 | Concrete Viaduct, Cribbing and | 9,039.86 | 9,039.86 | Masonry Wall, near Prescott | | | Beaver Valley Bridges | 32,000.00 | 29,808.58 | Scappoose Culvert | 1,834.60 | 1,834.60 | Goble Creek Bridge near Goble | 5,907.14 | 5,907.14 | Graham Creek Culvert near | 804.49 | 804.49 | Clatskanie | | | Coos County: | | | Coast Highway and Myrtle Point- | 180,235.18 | 180,235.18 | Coquille Road | | | Crook County: | | | Ochoco Canyon Forest Road | 52,500.00 | 3,053.72 | Project (Federal Government | | | cooperates on this project to | | | the amount of $17,500.00) | | | Deschutes County: | | | Cinder Macadam--Bend to LaPine | 20,183.60 | 20,183.60 | Douglas County: | | | Grading--Divide to Comstock | 19,146.74 | 19,146.74 | Grading and Macadam--Comstock | 80,000.00 | 79,092.87 | to Leona | | | Grading--Oakland to Yoncalla | 101,096.12 | 101,096.12 | Grading--Myrtle Creek to Dillard| 120,000.00 | 88,376.99 | Macadamizing--Divide to Comstock| 15,185.09 | 15,185.09 | Maintenance--Glendale to Stage | 74.65 | 74.65 | Road Pa.s.s | | | Umpqua River Bridges near | 45,500.00 | 24,802.85 | Dillard | | | Gilliam County: | | | Macadam--Condon to Thirty Mile | 32,500.00 | 31,096.05 | Creek | | | Hood River County: | | | Grading--Cascade Locks Section | 152,904.85 | 152,904.85 | Grading--Viento Section | 102,750.00 | 86,933.00 | Grading--Ruthton Hill Section | 107,000.00 | 90,257.53 | Macadam--Cascade Locks to Hood | 68,000.00 | 62,895.48 | River | | | Hood River Bridge | 48,000.00 | 40,528.29 | Jackson County: | | | Macadam--Siskiyou to California | 56,252.98 | 56,252.98 | Line | | | Ashland Under-crossing | 9,768.88 | 9,768.88 | Paving--Ashland Hill Section | 15,908.03 | 15,908.03 | Maintenance--Siskiyou Section | 748.34 | 748.34 | Josephine County: | | | Grading--Wolf Creek to Grave | 68,301.53 | 68,301.53 | Creek | | | Grading--Locust Hill Section | 4,869.97 | 4,869.97 | Miscellaneous charges on | 409.43 | 409.43 | construction in 1916 | | | Lake County: | | | Grading and Macadam--Lakeview | 15,391.67 | 15,391.67 | to Paisley | | | Lane County: | | | Macadam--Divide to Cottage Grove| 6,099.86 | 6,099.86 | Construction prior to 1917 | 424.44 | 424.44 | Lincoln County: | | | Grading--Pioneer Mountain | 2,054.05 | 2,054.05 | Section | | | Marion County: | | | Salem Bridge over Willamette | 223,902.99 | 223,902.99 | River | | | Polk County: | | | Approach to Salem Bridge | 4,548.10 | 4,548.10 | Reinforced Concrete Bridge at | 10,755.68 | 10,755.68 | Dallas | | | Reinforced Concrete Bridge | 1,898.17 | 1,898.17 | between Monmouth and Dallas | | | Charges on work prior to 1917 | 418.69 | 418.69 | Tillamook County: | | | Grading and Paving--Tillamook | 109,250.00 | 89,213.74 | to Hebo | | | Grading--Three Rivers Forest | 122,000.00 | 2,076.78 | Road Project (The Federal | | | Government cooperates on this | | | project to the amount of | | | $50,250.00.) | | | Umatilla County: | | | Paving--Wild Horse Creek Section| 162,626.56 | 162,626.56 | Union County: | | | Grading--La Grande to Hot Lake | 5,000.16 | 5,000.16 | Grading--Elgin-Minam Post Road | 41,151.00 | 3,838.44 | Project (The Federal | | | Government cooperates on this | | | project to the amount of | | | $20,575.50) | | | Grading--Union-Telocaset Post | 30,000.00 | 16,642.29 | Road Project (The Federal | | | Government cooperates on this | | | project to the amount of | | | $15,000.00.) | | | Washington County: | | | Grading and Paving--Multnomah | 332,000.00 | 278,976.93 | Co. Line to Newberg | | | Onion Flat Trestle near Sherwood| 8,372.22 | 8,372.22 | Tualatin River Bridge near | 12,968.60 | 12,968.60 | Tigardville | | | Fanno Creek Bridge near Tigard | 1,882.81 | 1,882.81 | Wheeler County: | | | Grading--c.u.mmins Hill Section | 14,532.35 | 14,532.35 | Macadam--c.u.mmins Hill Section | 34,000.00 | 32,465 44 | Grading--Bridge Creek Section | 24,235.45 | 24,235.45 | Resurfacing between Fossil and | 15,000.00 | 444.88 | Condon | | | Yamhill County: | | | Grading Rex to Newberg | 6,153.05 | 6,153.05 | Sheridan Paving, 1917 | 38,216.04 | 38,216.04 | Sheridan Paving, 1918 | 40,065.61 | 40,065.61 | Completion of Sour Gra.s.s Cut-off| 5,111.19 | 5,111.19 | +--------------+--------------+ |$3,795,861.61 |$3,187,463.23 | ----------------------------------+--------------+--------------+
==================================+=============================+ | STATE FUNDS | +--------------+--------------+ | State's | Expended | JOBS | share of | from | | estimated | State funds | | cost | to date | ----------------------------------+--------------+--------------+ Clackamas County: | | | Paving--Oregon City to Canby | $135,000.00 | $102,114.85 | Grading--Canemah Hill Section | 2,500.00 | 1,944.67 | Grading and Rock Crushing--New | 50,240.09 | 47,287.88 | Era | | | Grading--Multnomah Co. Line to | 507.98 | 507.98 | Oswego | | | Clatsop County: | | | Grading and Paving--Astoria to | 236,000.00 | 96,955.97 | Svensen | | | Macadamizing--Svensen to | 216,000.00 | 210,079.16 | Columbia Co. Line | | | John Day River Bridge east of | 25,000.00 | 21,051.52 | Astoria | | | Plympton Creek Bridge at | 6,413.19 | 6,413.19 | Westport | | | Big Creek Bridge near Knappa | 8,446.70 | 8,446.70 | Little Creek Culvert near Knappa| 929.69 | 929.69 | Miscellaneous charges on work | 247.94 | 247.94 | prior to 1917 | | | Columbia County: | | | Paving--Multnomah Co. Line to | 37,652.59 | 37,652.59 | Scappoose | | | Macadam--Clatsop Co. Line to | 121,000.00 | 118,922.90 | Clatskanie | | | Macadam--Clatskanie to Delena | 142,000.00 | 136,560.40 | Macadam--Delena to Goble | 49,955.08 | 49,955.08 | Macadam--Goble Section | 23,000.00 | 21,478.97 | Grading--Goble Section | 46,262.64 | 46,262.64 | Grading--Rainier Hill Section | 6,350.61 | 6,350.61 | Grading--Beaver Valley Section | 20,978.22 | 20,978.22 | Grading--Deer Island Section | 2,398.10 | 2,398.10 | Concrete Viaduct, Cribbing and | 9,039.86 | 9,039.86 | Masonry Wall, near Prescott | | | Beaver Valley Bridges | 32,000.00 | 29,808.58 | Scappoose Culvert | 1,834.60 | 1,834.60 | Goble Creek Bridge near Goble | 5,907.14 | 5,907.14 | Graham Creek Culvert near | 804.49 | 804.49 | Clatskanie | | | Coos County: | | | Coast Highway and Myrtle Point- | 9,453.35 | 9,453.35 | Coquille Road | | | Crook County: | | | Ochoco Canyon Forest Road | 17,500.00 | 3,053.72 | Project (Federal Government | | | cooperates on this project to | | | the amount of $17,500.00) | | | Deschutes County: | | | Cinder Macadam--Bend to LaPine | 20,183.60 | 20,183.60 | Douglas County: | | | Grading--Divide to Comstock | 2,027.30 | 2,027.30 | Grading and Macadam--Comstock | 5,650.28 | 4,743.15 | to Leona | | | Grading--Oakland to Yoncalla | 17,565.28 | 19,015.10 | Grading--Myrtle Creek to Dillard| 120,000.00 | 88,376.99 | Macadamizing--Divide to Comstock| 15,185.09 | 15,185.09 | Maintenance--Glendale to Stage | 74.65 | 74.65 | Road Pa.s.s | | | Umpqua River Bridges near | 45,500.00 | 24,802.85 | Dillard | | | Gilliam County: | | | Macadam--Condon to Thirty Mile | 32,500.00 | 31,096.05 | Creek | | | Hood River County: | | | Grading--Cascade Locks Section | 152,904.85 | 152,904.85 | Grading--Viento Section | 102,750.00 | 86,933.00 | Grading--Ruthton Hill Section | 107,000.00 | 90,257.53 | Macadam--Cascade Locks to Hood | 68,000.00 | 62,895.48 | River | | | Hood River Bridge | 43,968.49 | 36,559.80 | Jackson County: | | | Macadam--Siskiyou to California | 56,252.98 | 56,252.98 | Line | | | Ashland Under-crossing | 9,768.88 | 9,768.88 | Paving--Ashland Hill Section | 15,908.03 | 15,908.03 | Maintenance--Siskiyou Section | 748.34 | 748.34 | Josephine County: | | | Grading--Wolf Creek to Grave | 68,301.53 | 68,301.53 | Creek | | | Grading--Locust Hill Section | 4,869.97 | 4,869.97 | Miscellaneous charges on | 409.43 | 409.43 | construction in 1916 | | | Lake County: | | | Grading and Macadam--Lakeview | 15,391.67 | 15,391.67 | to Paisley | | | Lane County: | | | Macadam--Divide to Cottage Grove| 6,099.86 | 6,099.86 | Construction prior to 1917 | 424.44 | 424.44 | Lincoln County: | | | Grading--Pioneer Mountain | 2,054.05 | 2,054.05 | Section | | | Marion County: | | | Salem Bridge over Willamette | 108.00 | 108.00 | River | | | Polk County: | | | Approach to Salem Bridge | ... | ... | Reinforced Concrete Bridge at | 1.25 | 1.25 | Dallas | | | Reinforced Concrete Bridge | ... | ... | between Monmouth and Dallas | | | Charges on work prior to 1917 | 418.69 | 418.69 | Tillamook County: | | | Grading and Paving--Tillamook | 74,925.00 | 63,203.90 | to Hebo | | | Grading--Three Rivers Forest | 50,250.00 | 2,076.78 | Road Project (The Federal | | | Government cooperates on this | | | project to the amount of | | | $50,250.00.) | | | Umatilla County: | | | Paving--Wild Horse Creek Section| 162,626.56 | 162,626.56 | Union County: | | | Grading--La Grande to Hot Lake | 5,000.16 | 5,000.16 | Grading--Elgin-Minam Post Road | 20,575.50 | 3,838.44 | Project (The Federal | | | Government cooperates on this | | | project to the amount of | | | $20,575.50) | | | Grading--Union-Telocaset Post | 15,000.00 | 16,642.29 | Road Project (The Federal | | | Government cooperates on this | | | project to the amount of | | | $15,000.00.) | | | Washington County: | | | Grading and Paving--Multnomah | 322,605.00 | 269,581.93 | Co. Line to Newberg | | | Onion Flat Trestle near Sherwood| 8,372.22 | 8,372.22 | Tualatin River Bridge near | 12,968.60 | 12,968.60 | Tigardville | | | Fanno Creek Bridge near Tigard | 1,882.81 | 1,882.81 | Wheeler County: | | | Grading--c.u.mmins Hill Section | 7,005.15 | 7,005.15 | Macadam--c.u.mmins Hill Section | 34,000.00 | 32,465.44 | Grading--Bridge Creek Section | 14,235.45 | 14,235.45 | Resurfacing between Fossil and | 15,000.00 | 444.88 | Condon | | | Yamhill County: | | | Grading Rex to Newberg | ... | ... | Sheridan Paving, 1917 | 28,216.04 | 28,216.04 | Sheridan Paving, 1918 | 37,945.17 | 37,945.17 | Completion of Sour Gra.s.s cut-off| 5,111.19 | 5,111.19 | +--------------+--------------+ |$2,937,207.78 |$2,483,870.37 | ----------------------------------+--------------+--------------+
==================================+=========================+============ | COUNTY FUNDS |Construction +------------+------------+ engineering | County's | Expended | cost JOBS | share of | from | Included in | estimated |County funds| preceding | cost | to date | columns ----------------------------------+------------+------------+----------- Clackamas County: | | | Paving--Oregon City to Canby |$ ... |$ ... |$ 2,444.57 Grading--Canemah Hill Section | 25,000.00 | 22,092.53 | 1,944.67 Grading and Rock Crushing--New | 15,759.91 | 15,759.91 | 3,552.82 Era | | | Grading--Multnomah Co. Line to | 5,238.70 | 5,238.70 | 507.98 Oswego | | | Clatsop County: | | | Grading and Paving--Astoria to | ... | ... | 5,906.19 Svensen | | | Macadamizing--Svensen to | ... | ... | 4,443.18 Columbia Co. Line | | | John Day River Bridge east of | ... | ... | 734.91 Astoria | | | Plympton Creek Bridge at | ... | ... | 255.08 Westport | | | Big Creek Bridge near Knappa | ... | ... | 140.99 Little Creek Culvert near Knappa| ... | ... | 37.02 Miscellaneous charges on work | ... | ... | 25.00 prior to 1917 | | | Columbia County: | | | Paving--Multnomah Co. Line to | ... | ... | 1,364.28 Scappoose | | | Macadam--Clatsop Co. Line to | ... | ... | 554.62 Clatskanie | | | Macadam--Clatskanie to Delena | ... | ... | 5,998.96 Macadam--Delena to Goble | ... | ... | 2,902.35 Macadam--Goble Section | ... | ... | 548.12 Grading--Goble Section | ... | ... | 2,925.64 Grading--Rainier Hill Section | ... | ... | 468.88 Grading--Beaver Valley Section | ... | ... | ...
Grading--Deer Island Section | ... | ... | 163.30 Concrete Viaduct, Cribbing and | ... | ... | 580.53 Masonry Wall, near Prescott | | | Beaver Valley Bridges | ... | ... | 922.54 Scappoose Culvert | ... | ... | ...
Goble Creek Bridge near Goble | ... | ... | 77.47 Graham Creek Culvert near | ... | ... | 31.98 Clatskanie | | | Coos County: | | | Coast Highway and Myrtle Point- | 170,781.83 | 170,781.83 | 14,612.33 Coquille Road | | | Crook County: | | | Ochoco Canyon Forest Road | 17,500.00 | ... | ...
Project (Federal Government | | | cooperates on this project to | | | the amount of $17,500.00) | | | Deschutes County: | | | Cinder Macadam--Bend to LaPine | ... | ... | ...
Douglas County: | | | Grading--Divide to Comstock | 17,119.44 | 17,119.44 | 2,029.80 Grading and Macadam--Comstock | 74,349.72 | 74,349.72 | 4,766.13 to Leona | | | Grading--Oakland to Yoncalla | 83,530.84 | 82,081.02 | 5,864.31 Grading--Myrtle Creek to Dillard| ... | ... | 7,499.22 Macadamizing--Divide to Comstock| ... | ... | 302.09 Maintenance--Glendale to Stage | ... | ... | ...
Road Pa.s.s | | | Umpqua River Bridges near | ... | ... | 839.18 Dillard | | | Gilliam County: | | | Macadam--Condon to Thirty Mile | ... | ... | 1,292.39 Creek | | | Hood River County: | | | Grading--Cascade Locks Section | ... | ... | 8,744.41 Grading--Viento Section | ... | ... | 4,513.24 Grading--Ruthton Hill Section | ... | ... | 4,074.19 Macadam--Cascade Locks to Hood | ... | ... | 826.18 River | | | Hood River Bridge | 4,031.51 | 3,968.49 | 1,410.63 Jackson County: | | | Macadam--Siskiyou to California | ... | ... | 962.27 Line | | | Ashland Under-crossing | ... | ... | 275.21 Paving--Ashland Hill Section | ... | ... | 630.87 Maintenance--Siskiyou Section | ... | ... | Josephine County: | | | Grading--Wolf Creek to Grave | ... | ... | 4,872.94 Creek | | | Grading--Locust Hill Section | ... | ... | 162.88 Miscellaneous charges on | ... | ... | 219.23 construction in 1916 | | | Lake County: | | | Grading and Macadam--Lakeview | ... | ... | ...
to Paisley | | | Lane County: | | | Macadam--Divide to Cottage Grove| ... | ... | 175.84 Construction prior to 1917 | ... | ... | 30.64 Lincoln County: | | | Grading--Pioneer Mountain | ... | ... | ...
Section | | | Marion County: | | | Salem Bridge over Willamette | 223,794.99 | 223,794.99 | 265.26 River | | | Polk County: | | | Approach to Salem Bridge | 4,548.10 | 4,548.10 | ...
Reinforced Concrete Bridge at | 10,754.43 | 10,754.43 | 55.10 Dallas | | | Reinforced Concrete Bridge | 1,898.17 | 1,898.17 | ...
between Monmouth and Dallas | | | Charges on work prior to 1917 | ... | ... | 15.79 Tillamook County: | | | Grading and Paving--Tillamook | 34,325.00 | 26,009.84 | 6,391.47 to Hebo | | | Grading--Three Rivers Forest | 21,500.00 | ... | ...
Road Project (The Federal | | | Government cooperates on this | | | project to the amount of | | | $50,250.00.) | | | Umatilla County: | | | Paving--Wild Horse Creek Section| ... | ... | 2,609.88 Union County: | | | Grading--La Grande to Hot Lake | ... | ... | 821.68 Grading--Elgin-Minam Post Road | ... | ... | 377.80 Project (The Federal | | | Government cooperates on this | | | project to the amount of | | | $20,575.50) | | | Grading--Union-Telocaset Post | ... | ... | 1,183.22 Road Project (The Federal | | | Government cooperates on this | | | project to the amount of | | | $15,000.00.) | | | Washington County: | | | Grading and Paving--Multnomah | 9,395.00 | 9,395.00 | 9,445.56 Co. Line to Newberg | | | Onion Flat Trestle near Sherwood| ... | ... | 197.87 Tualatin River Bridge near | ... | ... | ...
Tigardville | | | Fanno Creek Bridge near Tigard | ... | ... | ...
Wheeler County: | | | Grading--c.u.mmins Hill Section | 7,527.20 | 7,527.20 | 1,402.73 Macadam--c.u.mmins Hill Section | ... | ... | 1,313.82 Grading--Bridge Creek Section | 10,000.00 | 10,000.00 | 635.30 Resurfacing between Fossil and | ... | ... | ...
Condon | | | Yamhill County: | | | Grading Rex to Newberg | 6,163.05 | 6,153.05 | ...
Sheridan Paving, 1917 | 10,000.00 | 10,000.00 | 1,131.35 Sheridan Paving, 1918 | 2,120.44 | 2,120.44 | 1,166.85 Completion of Sour Gra.s.s cut-off| ... | ... | 157.39 +------------+------------+----------- |$755,328.33 |$703,592.86 |$127,805.58 ----------------------------------+------------+------------+-----------
SUMMARY
Estimated total cost Expended to date
State $2,937,207.78 $2,483,870.37 County 755,328.33 703,592.86 Federal Government 103,325.50 ...
------------- ------------- Totals $3,795,861.61 $3,187,463.23
TABLE VI
EXPENDITURES FOR SURVEYS AND ENGINEERING COUNTY CONSTRUCTION DETAILED BY JOBS--DECEMBER 1, 1916, TO NOVEMBER 30, 1918