Home

Report of the Hoosac Tunnel and Troy and Greenfield Railroad Part 12

Report of the Hoosac Tunnel and Troy and Greenfield Railroad - novelonlinefull.com

You’re read light novel Report of the Hoosac Tunnel and Troy and Greenfield Railroad Part 12 online at NovelOnlineFull.com. Please use the follow button to get notification about the latest chapter next time when you visit NovelOnlineFull.com. Use F11 button to read novel in full-screen(PC only). Drop by anytime you want to read free – fast – latest novel. It’s great if you could leave a comment, share your opinion about the new chapters, new novel with others on the internet. We’ll do our best to bring you the finest, latest novel everyday. Enjoy

Stated and divided as above, the scrip which has been delivered on account of the railroad and tunnel, is as follows:--

========================================================================= On account On account of Date. On account of road west road of east Total.

of Tunnel. of Tunnel. of Tunnel. ------------------+------------+-------------+--------------+------------ 1858, October, 6, $50,000 00 $50,000 00 - $100,000 00 1859, October 4, 49,777 78 - - 49,777 78 1860, January 3, - - $50,222 22 50,222 22 1860, March 1, 80,222 22 - - 80,222 22 1860, October 8, 15,829 79 - 64,170 21 80,000 00 1860, Dec. 12, 5,580 37 - 112,197 40 117,777 77 1861, January 5, 2,781 99 - 30,601 34 38,883 83 1861, February 18, 2,545 83 - 23,281 95 25,777 78 1861, March 7, 2,052 82 - 19,724 95 21,777 77 1861, May 8, 5,061 65 - 80,438 35 85,500 00 1861, June 27, 2,831 89 - 84,668 11 37,500 00 1861, July 12, 3,497 61 - 90,002 39 93,500 00 +------------+-------------+--------------+------------ $170,131 95 $50,000 00 $505,256 92 $125,388 87 =========================================================================

The amount of State scrip which according to statutes, had been earned by the progress made towards constructing the tunnel before the surrender of the property to the State, may be stated as follows:--

Strictly considered, no portion of the tunnel at the East End was cut to the required size of 14 feet wide and 18 feet high, much of it was less than 12 feet wide, and some of it only about 13 feet high. At the entrance the excavation was so nearly sufficient that only a small amount more was required to bring it to full size, and had all the rest been well done, a not very exacting inspector might have pa.s.sed 25 feet of this as completed. The remaining 2,964 feet of penetration at this end could form no ground whatever for a claim as completed work.



At the West Shaft the heading had been driven in both directions 56-1/2 feet.

At the West End the total penetration had been 543 feet. Of this distance 26 feet had been arched with stone--40 feet is in rock, standing without support, and 477 feet is temporarily supported with timbers. Under the a.s.sumption that the 40 feet left unsupported is safe enough to be left permanently 80, then 66 feet was completed at this end, giving at all points a total penetration of 3,588-1/2 feet, of which, 91 feet was completed.

It is clear that the payment of $50,000, under the Act of April 5, 1854, for 1,000 feet of completed tunnel, was not earned.

Under the Act of 1859, scrip to the amount of $50,000 was to be delivered upon the completion of 1,000 feet of heading, and though the prior conditions of this Act had not been complied with, this amount may fairly be considered as having been earned.

The next payment of $30,222.22 for the completion of the second 1,000 feet of tunnel was clearly not earned.

All subsequent payments were made under the Act of April 4, 1860, providing for the payment of $30 per foot for heading and $20 per foot for the enlargement.

The total amount according to the several Acts is as follows:--

Under the Act of 1859,-- For 1,000 feet of heading, $50,000 00 Under Act of 1860,-- For balance of heading, say 2,588-1/2 feet, at $30 per foot, 77,655 00 For 91 feet of enlargement, at $20 per foot, 1,820 00 ----------- Total amount earned, $129,475 00

The amount of State scrip which under the statute had been earned by the progress made in constructing the railroad may now be considered.

The first payment of $50,000 under the Act of 1854, should have been for seven miles of completed railroad. The certificate of the engineer, upon which it was paid, gave (see page 82 of House doc.u.ment No. 185 for 1860,) the length of rails laid as upwards of seven miles; nothing in the certificate showed then any part of it was completed road, and upon investigation then made it proved that while most of it was done, a part near the west end of the tunnel "was not ten feet wide," and would cost several thousand dollars to complete it. It is clear that this payment had not then been earned in the manner provided by the statute.

The second payment was on account of the road, under the Act of 1859, for grading three miles of road, "said three miles being all situated within four miles of the point of commencement;" Page 30 of House doc.u.ment No. 185 for 1860 says of this grading, "the continuous line is interrupted by fourteen gaps of cuts and fills;" it is thus made up of fifteen separate pieces, avoiding all but the cheapest part of the work, and costing, as the contractor who did the work certifies, between $8,000 and $9,000. Under, to say the least, a somewhat liberal construction of the Act, $50,000 was said to have been earned by doing this grading.

All further deliveries of scrip have been under the Act of 1860, which provides that the $650,000 to be delivered on account of the road east of the tunnel shall be in proportion to the progress made upon the work. On page 15, (Senate doc.u.ment No. 93 for 1863,) the cost of the work done and materials furnished upon the road east of the tunnel is stated at $463,047 90

Deduct amount first expended, as testified by the contractor, for which the $50,000 was paid, say 8,500 00

Amount expended under the $650,000 appropriation, including the cost of worthless bridging and masonry, $454,547 90

The cost of completing the grading, bridging, masonry and superstructure upon this part of the road, as estimated by Mr. Laurie in 1862, was $370,970 80

Deduct the cost of a small change in the line, and of embankment washed away by the Deerfield River, 5,275 00

Sum required to complete the road upon the old line where the work stopped, $365,695 80

Amount already expended under the $650,000 appropriation, 454,547 90

Amount expended and to be expended at the then prices, $820,243 70

Of which 55 per cent. had been done when the work stopped, in July, 1861. 55-416/1000 per cent. therefore of the $650,000 had been earned, and this amounts to $360,204 00

The total amounts earned and paid compare as follows: Amount paid upon the tunnel, $170,131 95 Amount paid upon the road west of the tunnel, 50,000 00 Amount paid upon the road east of the tunnel, 505,256 92 ---------- $725,388 87

Amount earned upon the tunnel, $129,475 00 Amount earned upon the road west of tunnel, (not fully earned,) 50,000 00 Amount earned upon the road east of tunnel, (temporary work included,) 410,204 00 ---------- 589,679 00 ----------- $135,709 87 Overpayment in reckoning sterling exchange, say 44,000 00 Overpayment when the work stopped, in July, 1861, $179,709 87 ----------- Further payments made upon the same work under the law of 1862, 140,226 95 ----------- Total amount paid more than earned, $319,936 82

If proper deductions had been made from the amount earned on account of the unfinished condition of the seven miles west of the tunnel, on which the first $50,000 was paid, and on account of the worthless masonry and bridging which have been reckoned in at full cost, the overpayments would be shown more correctly to exceed in amount the sum of $350,000.

Please click Like and leave more comments to support and keep us alive.

RECENTLY UPDATED MANGA

Martial God Asura

Martial God Asura

Martial God Asura Chapter 6140: Meeting Red Cloak Again Author(s) : Kindhearted Bee,Shan Liang de Mi Feng,善良的蜜蜂 View : 57,348,221
My Girlfriend is a Zombie

My Girlfriend is a Zombie

My Girlfriend is a Zombie Chapter 823: Secrets Beneath the Ruins Author(s) : Dark Litchi, 黑暗荔枝, Dark Lychee View : 2,280,669
Legend of Swordsman

Legend of Swordsman

Legend of Swordsman Chapter 6352: Nine Physical Forms Author(s) : 打死都要钱, Mr. Money View : 10,248,310

Report of the Hoosac Tunnel and Troy and Greenfield Railroad Part 12 summary

You're reading Report of the Hoosac Tunnel and Troy and Greenfield Railroad. This manga has been translated by Updating. Author(s): Tappan Wentworth. Already has 975 views.

It's great if you read and follow any novel on our website. We promise you that we'll bring you the latest, hottest novel everyday and FREE.

NovelOnlineFull.com is a most smartest website for reading manga online, it can automatic resize images to fit your pc screen, even on your mobile. Experience now by using your smartphone and access to NovelOnlineFull.com